Why am I unable to select a stop while creating a certain task type even though I'm in the area?
Sometimes you may try to create a certain task type and you may not be able to select a specific stop. This could be due to a couple of reasons:
Example 1:
John Doe is assigned to the Lease Operator Team
John Doe is mapped to Northeast Midland Area via the Lease Operator Team
John Doe is trying to create a task for a Plunger Inspection Task Type
The Plunger Inspection Team is the assigned team to perform the Plunger Inspection Task Type
The task needs to be created on the Stop Tiger 15 which is in the Northeast Midland Area
However, John Doe is not able to select the Tiger 15 stop because
the Plunger Inspection Team is not mapped to the Northeast Midland Area
therefore nobody can perform a plunger inspection
Example 2:
John Doe is assigned to the Lease Operator Team
John Doe is mapped to Northeast Midland Area via the Lease Operator Team
John Doe is trying to create a task for a Plunger Inspection Task Type
The Plunger Inspection Team is the assigned team to perform the Plunger Inspection Task Type
The task needs to be created on the Stop Tiger 15
Stop Tiger 15 is mapped to 2 separate areas:
Northeast Midland Area
Midland Central Area
However, John Doe is not able to select the Tiger 15 stop because
Reason 1:
the Plunger Inspection Team is not mapped to the Northeast Midland Area
therefore nobody can perform a plunger inspection
Therefore John Doe cannot create a plunger inspection task on the Tiger 15 stop
Reason 2:
the Plunger Inspection Team is mapped to the Midland Central Area
But John Doe is not mapped to the Midland Central Area
Therefore, John Doe is unable to create a Plunger inspection task on the Tiger 15 stop